Pre-Purchase of 3 WasteWater Pumps and Associated Control Panel for Lift Station 22 Rehab Project
Submitted For:
Mike McKinley
Submitted By:
Mike McKinley, Public Works
Department:
Public Works
Information
ACTION REQUEST
Approve the pre-purchase of three (3) Wilo submersible wastewater pumps and one (1) associate electrical control panel for the Lift Station 22, Rehabilitation Project slated for later this calendar year (early next fiscal year).
BACKGROUND (Brief Summary)
As lead times have gotten longer over the past year, it has become necessary to pre-purchase these items in an attempt to shorten the total construction time.
Over the past 11 years the City has standardized its wastewater pumps to the Wilo brand and control panels to the Primex brand. K2 Services, LLC., is the only dealer authorized in this area. The total amount for the three pumps, controls, and related accessories is $167,842.32.
A letter of recommendation and sole source letter are attached for your review.
RECOMMENDATION
It is the recommendation of the Public Works Department and ARKK Engineers that the City Commission authorize the pre-purchase of these items from K2 Sevices, for the total amount of $167,842.32.
Fiscal Impact
Attachments